Posted By: SteamyTeaSchedule 2 (page 30)
• Provided that the renewable heating product has MCS certified or equivalent status at the time the scheme starts, the product will be eligible for support under the RHI.
• The installer of the product needs to have been MCS certified or equivalent at the time of the installation of the product. It will not be possible for transitional installations, which have not used MCS installers to be retrospectively approved by MCS and such installations will not be eligible for the RHI.
At the smaller scale, only MCS or equivalent certified equipment, which is installed by MCS or equivalent certified installers, will be eligible for support under the RHI. There is a risk that installers could breach the conditions of the scheme, for example, by incorrectly declaring that the equipment they’ve installed meets the eligibility requirements, which could mean the customer is not eligible for RHI support.
MCS certification for microgeneration heating equipment
13. The requirements of this regulation are that the plant for which accreditation is being sought is certified under the MCS and its installer was certified under MCS at the time of installation.
“commissioned” means, in relation to an eligible installation, the completion of such procedures and tests as constitute, at the time they are undertaken, the usual industry standards and practices for commissioning that type of eligible installation in order to demonstrate it is capable of operating and delivering heat to the premises or process for which it was installed;
Posted By: tedMCS do have a 'method' that allows someone who is not yet accredited to perform an installation, get it inspected by an MCS assessor, correct any mistakes, gain their installer accreditation and then re-commission the system in order for it to be eligible as an MCS certified system. But this is only allowed once for any particular installer.
Posted By: HairlocksI am about to start building. The company who are going to go the M&E are MCS accredited for PV panels, but have not got MCS accredited for Solar Thermal. Do I need to push them to get this before they do my install ET Panels, or can they retrospectivily certifiy it.
Posted By: tonyIs that relevant? Why shouldn't new build get RHI as well?